GOAL S.p.A. – Photovoltaic Installation

When roof constraints demand a different design approach

Starting from energy consumption, not panel count

The project was at GOAL S.p.A.’s Urgnano plant, which specialises in industrial dyeing and textile finishing. The aim was to generate renewable electricity, maximise self-consumption on site and shorten the investment payback period. The analysis led to a 246.71 kWp photovoltaic installation integrated with the existing electrical infrastructure.

The constraint overhead: the roof

Initial assessments showed that the roof area identified was too small to reach the required capacity. The main barrel-vaulted roof, in profiled metal sheeting with skylights, also had load-bearing limits. Adding more modules was not an option: the installation area had to be extended and the mounting arrangements rethought.

A solution built around the existing building

Working with the client and the structural engineer, we identified a second installation area on an existing canopy and optimised the working areas on the main roof. Ohm tech managed:

  • design and installation of the photovoltaic system;
  • assessments and mounting solutions compatible with the existing structures;
  • upgrades to the substation and protection systems to meet CEI 0-16 requirements;
  • modifications to the existing switchboard and integration of the new generation circuit;
  • grid connection applications, administrative requirements and support through to commissioning.

From technical solution to grid connection

The work went beyond installing modules and equipment. It also covered substation and protection upgrades and switchboard modifications. Grid connection applications and administrative requirements were handled in a coordinated way, giving the client a single point of contact throughout.

An investment with measurable returns

The system was installed within the agreed programme without interrupting production. Estimated annual generation is about 267 MWh, expected to cover around 65% of the plant’s electricity demand, with an estimated payback of around four years. The technical solution is directly tied to the financial case for the investment.

The project in numbers

  • 4 monthsOverall duration
  • 4 yearsEstimated payback period
  • 246 kWPhotovoltaic capacity
  • 65%Electricity requirements covered
  • LocationUrgnano (BG)
  • Project periodMay – September 2022
  • SectorTextile industry
  • ClientGoal S.p.A.
  • Contract value€300,000
  • Scope of workPhotovoltaic installation – revamping