Barilla Rubbiano Sauce Plant – Factory Expansion

Production kept running while construction went on

A deadline set by production

The works formed part of the expansion of Barilla’s Rubbiano plant, which produces sauces and pesto. Ohm tech was entrusted with the detailed installation design and the installation of the key electrical and specialist systems in the new production areas, together with testing, commissioning and start-up. The handover date had a clear purpose: the systems had to be ready in time for seasonal basil processing.

Construction had to adapt to production, not the other way round.

The plant stayed operational throughout. Access to work areas and the windows available to us depended on the production schedule, and some tasks could only be done during production shutdowns, at weekends or on public holidays. Alongside these tight time limits, coordination with other contractors and compliance with demanding technical standards, above all safety requirements, were essential.

Flexible teams, continuous planning

Multiple teams, working across several shifts where required, were coordinated by the Project Manager and Site Manager. Resources were scaled up or down according to the availability of work areas and progress on site.

The main activities included:

  • primary electrical distribution, cabling and cable containment;
  • electrical switchboards, and general and emergency lighting;
  • electrical installations serving plant rooms and mechanical systems;
  • integration with the new production lines;
  • detailed installation design, as-built documentation, commissioning and start-up.

When the design has to change

During the project, the proposed emergency lighting solution needed a substantial and urgent revision. Ohm tech developed an alternative, reviewed it with the stakeholders involved and rescheduled the works without affecting the overall completion date.

Ready when production needed us

The systems were completed on schedule, so the new production lines and basil processing could start without disrupting the plant’s normal operations. The project shows how we adapt project organisation and design to an industrial client’s real production schedule.

The project in numbers

  • 30+ kmCabling installed
  • 800+Lighting fixtures
  • 16+Peak workforce
  • LocationRubbiano (PR)
  • Project periodSeptember 2017 – August 2018
  • SectorFood manufacturing
  • ClientBarilla G.eR. F.lli S.p.A.
  • Contract value€650,000
  • Scope of workElectrical systems