RSD Casa dei Ragazzi IAMA Onlus

A deadline set by people’s needs, not only by construction

A building designed for 40 residents

The new residential care facility for people with disabilities in Olgiate Molgora covers more than 3,000 m² and is organised into two residential units. Ohm tech delivered the electrical and specialist systems throughout, integrating power distribution, safety and security systems and the technologies that support residents’ daily care.

Handover timed to the residents’ move

Forty residents had to leave their existing facility and move into the new one. The completion date was therefore more than a contractual milestone: it was a functional requirement. Every system had to be tested and fully operational so that care could continue from day one.

Building services and care support systems in one integrated infrastructure

Ohm tech managed detailed installation design, installation, interim inspections, as-built documentation, testing, commissioning and start-up, with one overriding aim: to bring the building into full operation. The scope included:

  • MV/LV transformer substation, standby generator, switchboards and electrical distribution;
  • lighting, mechanical systems and photovoltaic installations;
  • fire detection, voice evacuation, access control and CCTV;
  • structured cabling, video intercoms and room management systems;
  • nurse call systems and exit monitoring using wearable devices.

Technology that supports everyday care

Nurse call, access control, CCTV and wearable exit-monitoring devices were integrated with the building’s conventional services. Here, technology is not an add-on. It is part of the infrastructure that protects residents and staff.

Ready to welcome residents

Within 12 months, Ohm tech completed the systems in its scope and delivered the infrastructure the facility needed to open. Keeping to the programme allowed 40 residents to move in, a clear example of how reliable, timely delivery directly affects the quality of care.

The project in numbers

  • 11 monthsOverall duration
  • 40+ kmCabling installed
  • 60 kWPhotovoltaic capacity
  • 18+Peak workforce
  • LocationOlgiate Molgora
  • Project periodJuly 2022 – June 2023
  • SectorHealth and Social Care – Residential
  • ClientBorio Mangiarotti S.p.A.
  • Contract value€1,090,000
  • Scope of workElectrical and specialist systems