TOG Carlo De Benedetti Centre – Milan

Technology, safety and efficiency, fully integrated

One building, many requirements

The TOG Carlo De Benedetti Centre is dedicated to children and young people with complex neurological conditions. Its 3,000+ m² bring together care and rehabilitation areas, a hydrotherapy pool, immersive rooms and technology-focused spaces such as the FabLab. Ohm tech delivered the electrical and specialist building systems throughout, including detailed installation design, as-built documentation, testing, commissioning and start-up.

Complexity delivered in a ten-month programme

The systems had to perform reliably in care environments while supporting a wide range of technologies. Everything had to be coordinated within a demanding programme, with several contractors working on site. The challenge was not any single system but managing systems, procurement, people and schedules at the same time.

Coordinating systems and stakeholders

Ohm tech ran the systems in parallel through continuous technical and on-site coordination:

  • MV/LV transformer substation, switchboards and electrical distribution;
  • lighting, power systems and electrical installations serving mechanical systems;
  • fire detection, voice evacuation, intruder alarms, CCTV and access control;
  • data transmission and BMS supervisory control;
  • photovoltaic installations, electric vehicle charging and power supplies for rehabilitation and technology-focused spaces.

When the programme shapes procurement

Lead times for some equipment did not fit the construction programme. We identified alternatives that met the required technical specifications, assessed them and reviewed them with the client and the supervising engineer before implementation. At the same time, the site workforce was raised to a peak of more than 20.

Integrated systems, delivered on time

Within ten months, the systems in our scope were complete and the infrastructure needed to run the TOG Centre was operational. The project shows our ability to manage technology-intensive contracts by coordinating changes in design, procurement and site organisation.

The project in numbers

  • 10 monthsOverall duration
  • 60+ kmCabling installed
  • 100 kWPhotovoltaic capacity
  • 20+Personnel deployed
  • LocationMilan
  • Project periodJanuary – October 2023
  • SectorHealth and Social Care – Rehabilitation
  • ClientBorio Mangiarotti S.p.A.
  • Contract value€1,380,000
  • Scope of workElectrical and specialist systems