Bocconi University – 23 kV Transformer Substation Upgrade

Renewing the electrical heart of the campus with a single planned eight-hour shutdown

A critical substation that could not simply be switched off

Ohm tech upgraded the 23 kV transformer substation at Bocconi University in Milan, which supplies eight campus buildings through an open-ring distribution network. The aim was to replace the main electrical equipment (medium-voltage switchgear, transformers, MV and LV distribution circuits, the main LV switchboard and the essential loads switchboard), from dismantling the live installations through to commissioning the new configuration.

The real challenge: keeping the campus powered throughout the works

The campus power supply had to be maintained, with 23 kV equipment staying energised for most of the work. The preliminary design available also needed substantial revision to suit the real space constraints and construction programme. Activities were re-engineered and phased, including night-time and public-holiday working, with coordination with the building contractor on alterations to the plant rooms.

Rethinking the design to minimise downtime

Ohm tech developed the detailed installation design from the preliminary design, substantially revising several of the initial solutions. We designed and installed raised support frames for the medium-voltage switchgear and new floor cable trenches for low-voltage distribution. In parallel, temporary switchboards and distribution circuits kept the loads supplied throughout dismantling and replacement.

The scope of work included:

  • one eight-panel MV switchgear assembly and one eleven-panel main LV switchboard;
  • two 1,000 kVA transformers with their enclosures;
  • replacement and upgrading of medium- and low-voltage distribution circuits;
  • auxiliary command and control panels;
  • lighting and power systems;
  • supervisory control, testing, commissioning, start-up and final as-built documentation.

Eight hours for the critical changeover

The revised sequence confined the campus-wide outage to a single planned eight-hour window, coordinated with the replacement of the incoming 23 kV supply circuit by the distribution network operator, UNARETI. For this phase, four additional Ohm tech technicians reinforced the core team to coordinate disconnections, connections, checks and restoration of supply.

A more efficient, safer and easier-to-maintain substation

The upgrade finished ahead of schedule, with service continuous apart from the one planned shutdown. The new configuration uses two transformers in place of the previous three, with next-generation equipment, command and control systems and distribution circuits that improve efficiency, reliability, safety and maintainability. The project shows how we upgrade critical electrical infrastructure: start from the installation’s real constraints and turn them into a practical, achievable sequence of works.

The project in numbers

  • 2 months, with just 8 hours of downtimeOverall duration
  • 2 × 1,000 kVATransformers
  • 8Buildings supplied
  • 2+ kmCabling installed
  • 23 kVSupply voltage
  • LocationMilan
  • Project periodJuly – August 2022
  • SectorUniversity campus
  • ClientL. Bocconi University
  • Contract valueConfidential
  • Scope of work23 kV MV/LV transformer substation upgrade