WHA Logistics – Vidigulfo

A logistics hub reconfigured while the project is under way

From three independent units to one major logistics hub

The WHA project in Vidigulfo is a logistics hub of approximately 100,000 m², divided into units C1, C2 and C3, with offices, changing rooms, forklift charging rooms and numerous loading bays. Ohm tech was appointed to carry out the detailed engineering and installation design and to deliver the electrical and specialist systems and the safety and security systems, to requirements aligned with LEED Gold certification.

When the project changes after construction has begun

The first phase, launched in 2025, covered unit C3, while units C1 and C2 were to be defined later around the needs of future tenants. When about 70% of the building systems works in C3 were complete, activities were suspended for around eight months to allow remediation works. During the suspension, the intended uses of the facility changed several times, ending with the decision to give the entire hub to a single tenant, with new space layouts and new building systems requirements.

Rethinking electrical distribution before it became a constraint

From the outset, Ohm tech reviewed the proposed supply arrangement for C1, C2 and C3 and pointed out the cost and technical difficulties of an extensive low-voltage network. We proposed a dedicated transformer substation for each of the three units, which was then developed within the hub’s revised layout. When the project resumed in 2026, further design changes were agreed with the general contractor and the tenant: aluminum cables with equivalent electrical performance, modifications to the switchboards, and rerouting of the main supply circuits to improve load distribution and limit voltage drop.

Infrastructure designed for flexibility

The configuration now being installed includes:

  • one MV intake substation and three MV/LV transformer substations;
  • switchboards and main circuits for normal and safety power distribution;
  • general and emergency LED lighting with DALI dimming, occupancy sensors and light-level sensors;
  • power systems for warehouses and offices, with busbar trunking for forklift charging;
  • fire detection systems in warehouses and offices;
  • two photovoltaic installations with a combined capacity of approximately 100 kWp;
  • provision for electric vehicle charging, intruder alarms, CCTV and data transmission;
  • a BMS for energy consumption monitoring, lighting management and monitoring of building systems alarms.

Managing change while keeping the programme on track

The construction programme calls for simultaneous work across several units. The technical team is therefore updating the design and procuring materials to absorb layout changes and the tenant’s other requirements without disrupting installation. The project team comprises a Project Manager, a project technician, a design engineer, a Site Manager and several installation teams. The site workforce has peaked at around 20.

Progress is the measure of success.

The project is still under way. To date, Ohm tech has completed about 10 months of active work and around 60% of the contract scope. Despite the suspension and the later design revisions, progress remains in line with the overall construction programme, even with some warehouse handover dates brought forward. That is what makes this project so representative of our approach: adapting design, electrical distribution and site organisation to a changing context while keeping control of the end goal.

The project in numbers

  • 100,000 m²Site area
  • 60%Project progress
  • 100+ kmCabling installed
  • 2,500+Lighting fixtures
  • 20+Personnel deployed
  • LocationVidigulfo
  • Project periodFebruary 2025 – December 2026
  • SectorLogistics
  • ClientGSE Italia S.r.l.
  • Contract value€2,900,000
  • Scope of workElectrical and specialist systems, safety and security systems